14
Bosch Rexroth AG, RE 10522/01.2013
Bosch Rexroth AG
Mobile Applications
Glockeraustraße 4
89275 Elchingen, Germany
Phone.: +49-7308-82-0
info.ma@boschrexroth.de
www.boschrexroth.com
© This document, as well as the data, specifications and other information
set forth in it, are the exclusive property of Bosch Rexroth AG. It may not be
reproduced or given to third parties without its consent. The data specified
above only serve to describe the product. No statements concerning a
certain condition or suitability for a certain application can be derived from
our information. The information given does not release the user from the
obligation of own judgment and verification. It must be remembered that our
products are subject to a natural process of wear and aging.
PV7...A Series 1X / 2X | Variable vane pump, direct controlled
Commissioning instructions
Commissioning instructions
Air bleeding
▶ All of the PV7...A type vane pumps are self-priming.
▶ Before initial commissioning , the pump must be air-bled
to protect it against damage.
▶ During the initial commissioning, we recommend to fill
the housing through the case drain line. Take into
account the filter grade! This increases operating safety
and prevents wear in the case of unfavorable installation
conditions.
▶ If the pump flow is not bubble-free after approx.
20 seconds, the system has to be rechecked. After the
operating values have been reached, check the pipe
connections for leakage and check the operating tem-
perature.
Commissioning
▶ Check whether the system is thoroughly and properly
installed.
▶ Take into account the motor and pump direction of
rotation arrows.
▶ Start the pump without load and let the flow run with-
out pressure for a few seconds in order to provide suf-
ficient lubrication.
▶ On no account let the pump run without hydraulic fluid!
Note
▶ Adjustment, maintenance and repair of the pump
may only be carried out by authorized, trained and
instructed personnel!
▶ Use only original Rexroth spare parts!
▶ The pump may only be operated within the permissible
data.
▶ The pump may only be operated when in perfect
condition!
▶ When carrying out any work on the pump (e.g. mount-
ing and removal) switch the system to zero pressure
and isolate from the mains supply!
▶ Unauthorized conversions and changes, affecting the
safety and function are not permissible!
▶ Mount safety devices (e.g., coupling protection)!
▶ Do not remove any existing safety devices!
▶ The generally valid safety and accident prevention
regulations must be adhered to!